Construction schedules
2013 :
End of administrative and legal procedures
Beginning 2014 :
Preparatory work for construction site access – temporary interchange RD41-RN1 at the La Possession end, going south
Preparatory work for construction site access – construction site slip-road parallel to RN1 interchange of Port Est at the entrance of the coastal Road
Preparatory work for construction site access – restructuring of the interchange of La Grande Chaloupe
Construction of the 5400 m viaduct (preparation and mobilisation of construction site equipment)
Construction of the first 4 sections of the dike (preparation and mobilisation of construction site equipment)
During 2014 :
Construction of the interchange of La Possession
Construction of the viaduct of La Grande Chaloupe